CONTACT US ON

 +64 6 366 0318

Heaphy Track Pole Bridges

1 2 3 4 5 6 7

Client:

DOC TAKAKA

Engineer:

Brad Williamson-DOC Engineer

Location:

Heaphy Track, Gouland Downs, Kahurangi National Park

Work Description:

Construction of 5 bridge replacements throughout the Gouland Downs area on  the Heaphy Track.
4 x 10.5m pole bridges and 1x 21m with a central pier.  Remote access meant helicopter was used for all materials. 

Completed:

December 2016

 

ABOUT US

Edifice is New Zealand’s most experienced pedestrian bridge builder with hundreds of structures completed, including major contracts in Australia, and many throughout New Zealand's National Parks, some with World Heritage status.

READ MORE >>


TESTIMONIALS

icon speech
“...Edifice has a well-earned reputation for producing quality results on challenging projects and has a co-operative, can-do approach to issues that may arise...”
icon speech “...Edifice were very easy to work with in customizing the design to suit the Council’s specific requirements and at all stages of the project, I knew when the key milestones were going to be met. Installation was right on schedule and we couldnt be happier with the final result...”

READ MORE >>

CONTACT US

(06) 366 0318

Email: enquiries@edifice.co.nz